These US public-sector HVAC bids include Daikin preventive maintenance for White Plains schools, a mix of refurbishment and replacement at the University of North Florida, and a cooling system upgrade at Stratford’s Baldwin Center. The maintenance bid turns on technician coverage and manufacturer credentials. For the two equipment projects, check the equipment schedule, controls responsibilities and startup dates before you price. Coverage is selective and researched manually. Sources checked November 14, 2026.
Current US public-sector HVAC bids
| Buyer and work | Decisive requirement | Next response |
|---|---|---|
| White Plains City School District, New York. Daikin preventive maintenance and on-call service. | Daikin authorization and factory-trained employees. The technical specification prohibits subcontracting. | Sealed paper bid by November 23, 2026 at 1 p.m., White Plains prevailing time. |
| University of North Florida, Jacksonville. Two condensers and ten VAV boxes replaced, two air handlers refurbished. | Applicable Florida contractor license at bid opening, 5% bid security and separate prices for each scope item. | Workday bid by December 15, 2026 at 2 p.m. as listed. Pre-bid meeting November 23 and site visit November 24. |
| Town of Stratford, Connecticut. Replace HVAC equipment and ductwork at Baldwin Center. | 5% bid security, five comparable projects and a system operating by April 30, 2027. | Sealed paper bid by December 17, 2026 at 10 a.m. as listed. Optional site meeting November 17. |
The White Plains notice says prevailing time at the district. UNF’s public event schedule and Stratford’s bid cover give clock times without an explicit time zone. Confirm the local deadline and any changes before submitting.
HVAC maintenance and repair
White Plains schools — service Daikin VRV and VRF systems
The school district wants preventive maintenance, diagnostics, repairs, controls work and on-call service for its Daikin equipment. The technical specification requires current Daikin authorization, at least five years of continuous experience with the named systems, five comparable references and documented factory training for the proposed technicians. Staff handling refrigerant need applicable EPA certification. Line up qualified employees for diagnostics, commissioning and controls work, and check access to Daikin service tools and original equipment manufacturer (OEM) parts.
Confirm the service levels before costing the rota. General specifications call for emergency work within two hours and starting non-emergency or new work within 24 hours. The technical specifications separately give a four-hour on-site limit for critical failures and a next-business-day initial response for non-critical requests. Ask the district how those provisions apply together. The notice and the sample agreement also give different initial contract dates. Confirm the intended term before pricing annual coverage.
Price the annual maintenance program, technician labor and the OEM parts markup using the buyer’s bid form. Its comparison uses standard labor quantities and applies the markup to a $5,000 parts basis. Those are evaluation inputs. The technical specification also names an emergency labor rate, while the comparison form gives regular, overtime and weekend or holiday lines. Confirm where to quote emergency labor. The district pays for actual hours and materials and gives no minimum work commitment. Deliver the sealed F2027-76 package with $500 bid security by November 23 at 1 p.m. to the district Business Office at 5 Homeside Lane. The district purchasing page links to the revised bid package and is a route for addenda.
HVAC equipment replacement and refurbishment
University of North Florida — refurbish the air handlers and replace selected equipment
At UNF’s Golf Center in Jacksonville, the contractor replaces two direct-expansion condensers and ten variable-air-volume boxes, and refurbishes two existing air handlers. The air-handler work includes new coils and fan arrays, repairs to cabinets and drain pans, and testing and commissioning. The university supplies and installs specific building automation controls and programming. Check the responsibility split for control wiring, actuators and coordination with the university’s controls contractor. Use the attached mechanical schedules to confirm capacity and the bid specification to price the current scope.
UNF asks for firm fixed pricing by scope item. Its coil options carry different minimum warranties from final acceptance. Microchannel coils require ten years of parts, labor and refrigerant coverage. Copper-tube/aluminum-fin coils require five years of that coverage. Include night and weekend work in the estimate and plan for substantial completion within 90 calendar days of the notice to proceed, with final completion another 30 days later. The public event calls for applicable state licensure at opening and 5% bid security.
Workday event 2229 is open under ITB 27-06. The public description gives a November 23 online pre-bid meeting and a November 24 site visit, both at 11:30 a.m., and a December 2 noon question cutoff. Confirm attendance and RSVP instructions with the current event. Submit electronically by December 15 at 2 p.m. Use the signed bid form and each required upload in Workday. The event’s public scope, original overview, mechanical schedule and coil data were available for review. Check the response workspace for current forms and notices.
Stratford Baldwin Center — plan for an April cooling start
The town is buying a single-prime HVAC upgrade for the Baldwin Senior Center. The work includes removing equipment and ductwork in the mechanical room, installing new air handlers and 40- and 50-ton air-cooled condensing units, and completing associated piping, controls, duct and electrical work. Check the equipment schedules and controls sequence, including testing and balancing. The milestone schedule calls for shop drawings by January 29 and the system fully operational by April 30, 2027, with closeout by May 28.
Price the installation around the procurement lead times, equipment access, electrical changes and downtime needed for startup. The town’s official package for Bid 2027-10 asks for 5% bid security, an AIA contractor qualification statement, five comparable jobs from the last three years and subcontractor details. Check the bid package thresholds for state prequalification and post-award bonding.
The optional site meeting is November 17 at 10 a.m. at 1000 West Broad Street. Written questions close December 8 at noon, and the town expects a response by addendum around December 14. Deliver the sealed bid to the Purchasing Department at 2725 Main Street, Room 104, before the stated 10 a.m. cutoff on December 17. Check the town purchasing page for any addenda.
Prepare your HVAC bid
- For service, cost coverage by building and equipment type. Match the asset list to preventive tasks and frequencies. Show which staff cover controls and refrigeration, and how you will dispatch emergency calls when a technician is already on a job. Map regular and after-hours rates to the buyer’s form.
- For equipment work, assign each connection and test. Check capacity, voltage, clearances and lead times against the issued schedules. Identify who supplies control hardware, wiring and programming. Put access, outages, testing, balancing and commissioning on the schedule before committing to a completion date.
- Track what goes in with the bid. Gather license and factory training records, surety, references, subcontractor disclosures and addendum acknowledgments. DeepRFP can help extract those requirements from the bid documents into a checklist for the estimator and project manager to review.
For more opportunities, search SAM.gov under NAICS 238220 and check local school, college and municipal purchasing portals for mechanical service and HVAC equipment work. Verify the first participation deadline in the live buyer record.